Wroclaw Intermodal Hub Upgrade

City: Wroclaw Impact: 95 Completion: 55% Budget: 5,800,000 EUR

Project Analytics

Beneficiaries (est.)

17,100

CO2 Reduction / year

660 t

On-time Confidence

62%

Readiness Index

81

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
55%
Impact Score
95
Budget Utilization (estimated)
50.6%
50.6%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
85
Incidents current (annual)
38

Baseline vs Current vs Target

Ridership (daily)489005420061500
Incidents (annual)1057545
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:55

Geo and Infrastructure Context

CityWroclaw
Latitude51.1259
Longitude17.0385
Primary corridor length11.9 km
Stops/intersections affected14
Maintenance classPriority A
Program start year2023
Target completion year2027
Modal shift KPI30%
CO2 reduction KPI660 tons/year
Safety improvement KPI34%
Funding requested6,496,000 EUR
Funding secured5,336,000 EUR
Funding disbursed3,190,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 07:31:55

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 03:41:55

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-02 10:25:15

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Station integration improvements for rail, bus, bike, and park-and-ride transfer efficiency. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.