Warsaw Smart Intersection Safety Program

City: Warsaw Impact: 78 Completion: 55% Budget: 2,840,000 EUR

Project Analytics

Beneficiaries (est.)

14,040

CO2 Reduction / year

308 t

On-time Confidence

62%

Readiness Index

70

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
55%
Impact Score
78
Budget Utilization (estimated)
50.6%
50.6%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
85
Incidents current (annual)
46

Baseline vs Current vs Target

Ridership (daily)451604978056400
Incidents (annual)1229262
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityWarsaw
Latitude52.2387
Longitude21.0122
Primary corridor length9.8 km
Stops/intersections affected14
Maintenance classPriority B
Program start year2021
Target completion year2025
Modal shift KPI14%
CO2 reduction KPI308 tons/year
Safety improvement KPI18%
Funding requested3,180,800 EUR
Funding secured2,612,800 EUR
Funding disbursed1,562,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 02:11:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 19:41:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-02 01:31:54

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Predictive signal logic, pedestrian priority cycles, and integrated incident response at key nodes. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.