Torun Metrobus Reliability Corridor

City: Torun Impact: 76 Completion: 73% Budget: 18,010,000 EUR

Project Analytics

Beneficiaries (est.)

13,680

CO2 Reduction / year

2112 t

On-time Confidence

76.4%

Readiness Index

75

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
73%
Impact Score
76
Budget Utilization (estimated)
67.16%
67.16%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
67
Incidents current (annual)
37

Baseline vs Current vs Target

Ridership (daily)447204926055800
Incidents (annual)1249464
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:57

Geo and Infrastructure Context

CityTorun
Latitude53.0318
Longitude18.6204
Primary corridor length9.5 km
Stops/intersections affected18
Maintenance classPriority B
Program start year2019
Target completion year2023
Modal shift KPI30%
CO2 reduction KPI2112 tons/year
Safety improvement KPI28%
Funding requested20,171,200 EUR
Funding secured16,569,200 EUR
Funding disbursed13,147,300 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-02 05:31:57

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-31 12:41:57

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 23:05:17

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Dedicated busway lanes, dynamic headway management, and dispatch integration on strategic corridors. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.