Poznan Intermodal Hub Upgrade

City: Poznan Impact: 79 Completion: 28% Budget: 6,725,000 EUR

Project Analytics

Beneficiaries (est.)

14,220

CO2 Reduction / year

770 t

On-time Confidence

40.4%

Readiness Index

61.2

Lifecycle Stage

Funded

KPI Data Quality

100/100
Loading forecast panel...
Completion
28%
Impact Score
79
Budget Utilization (estimated)
25.76%
25.76%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
112
Incidents current (annual)
60

Baseline vs Current vs Target

Ridership (daily)453805004056700
Incidents (annual)1219161
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:55

Geo and Infrastructure Context

CityPoznan
Latitude52.4154
Longitude16.9362
Primary corridor length9.9 km
Stops/intersections affected7
Maintenance classPriority B
Program start year2021
Target completion year2025
Modal shift KPI13%
CO2 reduction KPI770 tons/year
Safety improvement KPI39%
Funding requested7,532,000 EUR
Funding secured6,187,000 EUR
Funding disbursed1,883,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 09:11:55

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 06:11:55

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-02 13:11:55

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Station integration improvements for rail, bus, bike, and park-and-ride transfer efficiency. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.