Plock Low-Emission Mobility Zone

City: Plock Impact: 81 Completion: 37% Budget: 20,230,000 EUR

Project Analytics

Beneficiaries (est.)

14,580

CO2 Reduction / year

2376 t

On-time Confidence

47.6%

Readiness Index

65.6

Lifecycle Stage

Funded

KPI Data Quality

100/100
Loading forecast panel...
Completion
37%
Impact Score
81
Budget Utilization (estimated)
34.04%
34.04%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
103
Incidents current (annual)
54

Baseline vs Current vs Target

Ridership (daily)458205056057300
Incidents (annual)1198959
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:57

Geo and Infrastructure Context

CityPlock
Latitude52.5648
Longitude19.7284
Primary corridor length10.1 km
Stops/intersections affected9
Maintenance classPriority B
Program start year2017
Target completion year2021
Modal shift KPI20%
CO2 reduction KPI2376 tons/year
Safety improvement KPI40%
Funding requested22,657,600 EUR
Funding secured18,611,600 EUR
Funding disbursed7,485,100 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-02 09:31:57

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-31 18:41:57

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-04 05:45:17

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Access management, clean fleet prioritization, and neighborhood traffic calming in dense districts. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.