Urban Insight Hub
← Back to Dashboard

Opole Smart Intersection Safety Program

City: Opole Impact: 86 Completion: 82% Budget: 16,715,000 EUR

Project Analytics

Beneficiaries (est.)

15,480

CO2 Reduction / year

1958 t

On-time Confidence

83.6%

Readiness Index

84.6

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
82%
Impact Score
86
Budget Utilization (estimated)
75.44%
75.44%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
58
Incidents current (annual)
29

Baseline vs Current vs Target

Ridership (daily)469205186058800
Incidents (annual)1148454
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityOpole
Latitude50.6841
Longitude17.9543
Primary corridor length10.8 km
Stops/intersections affected21
Maintenance classPriority A
Program start year2019
Target completion year2023
Modal shift KPI23%
CO2 reduction KPI1958 tons/year
Safety improvement KPI21%
Funding requested18,720,800 EUR
Funding secured15,377,800 EUR
Funding disbursed13,706,300 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-02 03:11:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-31 09:11:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 19:11:56

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Predictive signal logic, pedestrian priority cycles, and integrated incident response at key nodes. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.