Odessa Universal Access Transit Upgrade

City: Odessa Impact: 79 Completion: 38% Budget: 6,000,000 EUR

Project Analytics

Beneficiaries (est.)

14,220

CO2 Reduction / year

500 t

On-time Confidence

48.4%

Readiness Index

64.7

Lifecycle Stage

Funded

KPI Data Quality

100/100
Loading forecast panel...
Completion
38%
Impact Score
79
Budget Utilization (estimated)
34.96%
34.96%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
102
Incidents current (annual)
55

Baseline vs Current vs Target

Ridership (daily)453805004056700
Incidents (annual)1219161
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:53

Geo and Infrastructure Context

CityOdessa
Latitude46.5045
Longitude30.7233
Primary corridor length9.9 km
Stops/intersections affected10
Maintenance classPriority B
Program start year2019
Target completion year2022
Modal shift KPI10%
CO2 reduction KPI500 tons/year
Safety improvement KPI32%
Funding requested6,720,000 EUR
Funding secured5,520,000 EUR
Funding disbursed2,280,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 16:31:53

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 05:11:53

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 09:25:13

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Barrier-free stop redesign, tactile guidance deployment, and platform-level accessibility retrofits. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.