Kielce Metrobus Reliability Corridor

City: Kielce Impact: 93 Completion: 82% Budget: 15,235,000 EUR

Project Analytics

Beneficiaries (est.)

16,740

CO2 Reduction / year

1782 t

On-time Confidence

83.6%

Readiness Index

89.2

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
82%
Impact Score
93
Budget Utilization (estimated)
75.44%
75.44%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
58
Incidents current (annual)
26

Baseline vs Current vs Target

Ridership (daily)484605368060900
Incidents (annual)1077747
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityKielce
Latitude50.8841
Longitude20.6616
Primary corridor length11.6 km
Stops/intersections affected21
Maintenance classPriority A
Program start year2018
Target completion year2022
Modal shift KPI15%
CO2 reduction KPI1782 tons/year
Safety improvement KPI49%
Funding requested17,063,200 EUR
Funding secured14,016,200 EUR
Funding disbursed12,492,700 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-02 00:31:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-31 05:11:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 14:45:16

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Dedicated busway lanes, dynamic headway management, and dispatch integration on strategic corridors. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.