Kielce Intermodal Hub Upgrade

City: Kielce Impact: 74 Completion: 46% Budget: 15,975,000 EUR

Project Analytics

Beneficiaries (est.)

13,320

CO2 Reduction / year

1870 t

On-time Confidence

54.8%

Readiness Index

64.2

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
46%
Impact Score
74
Budget Utilization (estimated)
42.32%
42.32%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
94
Incidents current (annual)
53

Baseline vs Current vs Target

Ridership (daily)442804874055200
Incidents (annual)1269666
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityKielce
Latitude50.8661
Longitude20.6616
Primary corridor length9.3 km
Stops/intersections affected12
Maintenance classPriority B
Program start year2022
Target completion year2026
Modal shift KPI19%
CO2 reduction KPI1870 tons/year
Safety improvement KPI17%
Funding requested17,892,000 EUR
Funding secured14,697,000 EUR
Funding disbursed7,348,500 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-02 01:51:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-31 07:11:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 16:58:36

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Station integration improvements for rail, bus, bike, and park-and-ride transfer efficiency. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.