Kharkiv Safe School Corridor Program

City: Kharkiv Impact: 81 Completion: 45% Budget: 6,230,000 EUR

Project Analytics

Beneficiaries (est.)

14,580

CO2 Reduction / year

516 t

On-time Confidence

54%

Readiness Index

68.4

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
45%
Impact Score
81
Budget Utilization (estimated)
41.4%
41.4%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
95
Incidents current (annual)
50

Baseline vs Current vs Target

Ridership (daily)458205056057300
Incidents (annual)1198959
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:53

Geo and Infrastructure Context

CityKharkiv
Latitude49.9935
Longitude36.2434
Primary corridor length10.1 km
Stops/intersections affected11
Maintenance classPriority B
Program start year2020
Target completion year2023
Modal shift KPI11%
CO2 reduction KPI516 tons/year
Safety improvement KPI33%
Funding requested6,977,600 EUR
Funding secured5,731,600 EUR
Funding disbursed2,803,500 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 16:51:53

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 05:41:53

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 09:58:33

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Raised crossings, tactical curb extensions, speed governance, and school-zone signal timing updates. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.