Ivano-Frankivsk Safe School Corridor Program

City: Ivano-Frankivsk Impact: 72 Completion: 52% Budget: 8,530,000 EUR

Project Analytics

Beneficiaries (est.)

12,960

CO2 Reduction / year

676 t

On-time Confidence

59.6%

Readiness Index

65

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
52%
Impact Score
72
Budget Utilization (estimated)
47.84%
47.84%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
88
Incidents current (annual)
51

Baseline vs Current vs Target

Ridership (daily)438404822054600
Incidents (annual)1289868
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityIvano-Frankivsk
Latitude48.9336
Longitude24.7501
Primary corridor length9 km
Stops/intersections affected13
Maintenance classPriority B
Program start year2020
Target completion year2023
Modal shift KPI21%
CO2 reduction KPI676 tons/year
Safety improvement KPI13%
Funding requested9,553,600 EUR
Funding secured7,847,600 EUR
Funding disbursed4,435,600 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 20:11:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 10:41:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 15:31:54

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Raised crossings, tactical curb extensions, speed governance, and school-zone signal timing updates. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.