Bydgoszcz Tram Grid Modernization Package

City: Bydgoszcz Impact: 67 Completion: 55% Budget: 11,720,000 EUR

Project Analytics

Beneficiaries (est.)

12,060

CO2 Reduction / year

1364 t

On-time Confidence

62%

Readiness Index

62.8

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
55%
Impact Score
67
Budget Utilization (estimated)
50.6%
50.6%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
85
Incidents current (annual)
52

Baseline vs Current vs Target

Ridership (daily)427404692053100
Incidents (annual)13310373
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityBydgoszcz
Latitude53.1325
Longitude18.0084
Primary corridor length8.4 km
Stops/intersections affected14
Maintenance classPriority B
Program start year2020
Target completion year2024
Modal shift KPI18%
CO2 reduction KPI1364 tons/year
Safety improvement KPI30%
Funding requested13,126,400 EUR
Funding secured10,782,400 EUR
Funding disbursed6,446,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 18:11:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 19:41:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 04:11:56

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Track renewal, platform reconfiguration, and rolling signal optimization for tram corridors. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.