Bydgoszcz Intermodal Hub Upgrade

City: Bydgoszcz Impact: 76 Completion: 82% Budget: 12,275,000 EUR

Project Analytics

Beneficiaries (est.)

13,680

CO2 Reduction / year

1430 t

On-time Confidence

83.6%

Readiness Index

78.1

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
82%
Impact Score
76
Budget Utilization (estimated)
75.44%
75.44%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
58
Incidents current (annual)
32

Baseline vs Current vs Target

Ridership (daily)447204926055800
Incidents (annual)1249464
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityBydgoszcz
Latitude53.1325
Longitude18.0414
Primary corridor length9.5 km
Stops/intersections affected21
Maintenance classPriority B
Program start year2023
Target completion year2027
Modal shift KPI21%
CO2 reduction KPI1430 tons/year
Safety improvement KPI33%
Funding requested13,748,000 EUR
Funding secured11,293,000 EUR
Funding disbursed10,065,500 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 19:11:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 21:11:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 05:51:56

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Station integration improvements for rail, bus, bike, and park-and-ride transfer efficiency. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.