Bialystok Low-Emission Mobility Zone

City: Bialystok Impact: 86 Completion: 19% Budget: 10,980,000 EUR

Project Analytics

Beneficiaries (est.)

15,480

CO2 Reduction / year

1276 t

On-time Confidence

33.2%

Readiness Index

62.6

Lifecycle Stage

Funded

KPI Data Quality

100/100
Loading forecast panel...
Completion
19%
Impact Score
86
Budget Utilization (estimated)
17.48%
17.48%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
121
Incidents current (annual)
60

Baseline vs Current vs Target

Ridership (daily)469205186058800
Incidents (annual)1148454
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityBialystok
Latitude53.1325
Longitude23.1688
Primary corridor length10.8 km
Stops/intersections affected6
Maintenance classPriority A
Program start year2023
Target completion year2027
Modal shift KPI14%
CO2 reduction KPI1276 tons/year
Safety improvement KPI26%
Funding requested12,297,600 EUR
Funding secured10,101,600 EUR
Funding disbursed2,086,200 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 16:51:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 17:41:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 01:58:36

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Access management, clean fleet prioritization, and neighborhood traffic calming in dense districts. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.