Chernihiv Safe School Corridor Program

City: Chernihiv Impact: 92 Completion: 59% Budget: 10,830,000 EUR

Project Analytics

Beneficiaries (est.)

16,560

CO2 Reduction / year

836 t

On-time Confidence

65.2%

Readiness Index

80.5

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
59%
Impact Score
92
Budget Utilization (estimated)
54.28%
54.28%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
81
Incidents current (annual)
37

Baseline vs Current vs Target

Ridership (daily)482405342060600
Incidents (annual)1087848
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityChernihiv
Latitude51.5202
Longitude31.3023
Primary corridor length11.5 km
Stops/intersections affected15
Maintenance classPriority A
Program start year2020
Target completion year2023
Modal shift KPI13%
CO2 reduction KPI836 tons/year
Safety improvement KPI23%
Funding requested12,129,600 EUR
Funding secured9,963,600 EUR
Funding disbursed6,389,700 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 23:31:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 15:41:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 21:05:14

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Raised crossings, tactical curb extensions, speed governance, and school-zone signal timing updates. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.