Poltava Universal Access Transit Upgrade

City: Poltava Impact: 90 Completion: 52% Budget: 10,600,000 EUR

Project Analytics

Beneficiaries (est.)

16,200

CO2 Reduction / year

820 t

On-time Confidence

59.6%

Readiness Index

76.7

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
52%
Impact Score
90
Budget Utilization (estimated)
47.84%
47.84%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
88
Incidents current (annual)
41

Baseline vs Current vs Target

Ridership (daily)478005290060000
Incidents (annual)1108050
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityPoltava
Latitude49.5993
Longitude34.5514
Primary corridor length11.3 km
Stops/intersections affected13
Maintenance classPriority A
Program start year2019
Target completion year2022
Modal shift KPI12%
CO2 reduction KPI820 tons/year
Safety improvement KPI22%
Funding requested11,872,000 EUR
Funding secured9,752,000 EUR
Funding disbursed5,512,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 23:11:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 15:11:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 20:31:54

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Barrier-free stop redesign, tactile guidance deployment, and platform-level accessibility retrofits. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.