Ivano-Frankivsk Electric Bus Priority Network

City: Ivano-Frankivsk Impact: 74 Completion: 59% Budget: 8,760,000 EUR

Project Analytics

Beneficiaries (est.)

13,320

CO2 Reduction / year

692 t

On-time Confidence

65.2%

Readiness Index

68.8

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
59%
Impact Score
74
Budget Utilization (estimated)
54.28%
54.28%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
81
Incidents current (annual)
46

Baseline vs Current vs Target

Ridership (daily)442804874055200
Incidents (annual)1269666
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityIvano-Frankivsk
Latitude48.9446
Longitude24.7111
Primary corridor length9.3 km
Stops/intersections affected15
Maintenance classPriority B
Program start year2021
Target completion year2024
Modal shift KPI22%
CO2 reduction KPI692 tons/year
Safety improvement KPI14%
Funding requested9,811,200 EUR
Funding secured8,059,200 EUR
Funding disbursed5,168,400 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 20:31:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 11:11:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 16:05:14

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Dedicated lanes, queue jumps, and adaptive signal priority integrated with dispatch telemetry. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.