Kharkiv Protected Cycling Arc

City: Kharkiv Impact: 85 Completion: 59% Budget: 6,690,000 EUR

Project Analytics

Beneficiaries (est.)

15,300

CO2 Reduction / year

548 t

On-time Confidence

65.2%

Readiness Index

75.9

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
59%
Impact Score
85
Budget Utilization (estimated)
54.28%
54.28%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
81
Incidents current (annual)
41

Baseline vs Current vs Target

Ridership (daily)467005160058500
Incidents (annual)1158555
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:53

Geo and Infrastructure Context

CityKharkiv
Latitude50.0155
Longitude36.2694
Primary corridor length10.6 km
Stops/intersections affected15
Maintenance classPriority B
Program start year2022
Target completion year2025
Modal shift KPI13%
CO2 reduction KPI548 tons/year
Safety improvement KPI35%
Funding requested7,492,800 EUR
Funding secured6,154,800 EUR
Funding disbursed3,947,100 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 17:31:53

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 06:41:53

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 11:05:13

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Continuous protected cycle tracks linking housing districts to business zones and transit nodes. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.