Lviv Electric Bus Priority Network

City: Lviv Impact: 82 Completion: 73% Budget: 3,010,000 EUR

Project Analytics

Beneficiaries (est.)

14,760

CO2 Reduction / year

292 t

On-time Confidence

76.4%

Readiness Index

78.9

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
73%
Impact Score
82
Budget Utilization (estimated)
67.16%
67.16%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
67
Incidents current (annual)
35

Baseline vs Current vs Target

Ridership (daily)460405082057600
Incidents (annual)1188858
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:53

Geo and Infrastructure Context

CityLviv
Latitude49.8507
Longitude24.0687
Primary corridor length10.3 km
Stops/intersections affected18
Maintenance classPriority B
Program start year2021
Target completion year2024
Modal shift KPI15%
CO2 reduction KPI292 tons/year
Safety improvement KPI19%
Funding requested3,371,200 EUR
Funding secured2,769,200 EUR
Funding disbursed2,197,300 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-02-28 12:11:53

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-28 22:41:53

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-01 02:11:53

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Dedicated lanes, queue jumps, and adaptive signal priority integrated with dispatch telemetry. Program includes stakeholder engagement, tactical pilots, KPI monitoring, and phased scaling.