Gdynia Low-Emission Mobility Zone

City: Gdynia Impact: 85 Completion: 37% Budget: 12,830,000 EUR

Project Analytics

Beneficiaries (est.)

15,300

CO2 Reduction / year

1496 t

On-time Confidence

47.6%

Readiness Index

68.2

Lifecycle Stage

Funded

KPI Data Quality

100/100
Loading forecast panel...
Completion
37%
Impact Score
85
Budget Utilization (estimated)
34.04%
34.04%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
103
Incidents current (annual)
52

Baseline vs Current vs Target

Ridership (daily)467005160058500
Incidents (annual)1158555
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityGdynia
Latitude54.5279
Longitude18.5525
Primary corridor length10.6 km
Stops/intersections affected9
Maintenance classPriority B
Program start year2019
Target completion year2023
Modal shift KPI24%
CO2 reduction KPI1496 tons/year
Safety improvement KPI36%
Funding requested14,369,600 EUR
Funding secured11,803,600 EUR
Funding disbursed4,747,100 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 20:11:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 22:41:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 07:31:56

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Access management, clean fleet prioritization, and neighborhood traffic calming in dense districts. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.