Bydgoszcz Low-Emission Mobility Zone

City: Bydgoszcz Impact: 70 Completion: 64% Budget: 11,905,000 EUR

Project Analytics

Beneficiaries (est.)

12,600

CO2 Reduction / year

1386 t

On-time Confidence

69.2%

Readiness Index

67.9

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
64%
Impact Score
70
Budget Utilization (estimated)
58.88%
58.88%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
76
Incidents current (annual)
45

Baseline vs Current vs Target

Ridership (daily)434004770054000
Incidents (annual)13010070
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:56

Geo and Infrastructure Context

CityBydgoszcz
Latitude53.1415
Longitude18.0194
Primary corridor length8.8 km
Stops/intersections affected16
Maintenance classPriority B
Program start year2021
Target completion year2025
Modal shift KPI19%
CO2 reduction KPI1386 tons/year
Safety improvement KPI31%
Funding requested13,333,600 EUR
Funding secured10,952,600 EUR
Funding disbursed7,619,200 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 18:31:56

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 20:11:56

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-03 04:45:16

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Access management, clean fleet prioritization, and neighborhood traffic calming in dense districts. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.