Poznan Tram Grid Modernization Package

City: Poznan Impact: 70 Completion: 73% Budget: 6,170,000 EUR

Project Analytics

Beneficiaries (est.)

12,600

CO2 Reduction / year

704 t

On-time Confidence

76.4%

Readiness Index

71.1

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
73%
Impact Score
70
Budget Utilization (estimated)
67.16%
67.16%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
67
Incidents current (annual)
39

Baseline vs Current vs Target

Ridership (daily)434004770054000
Incidents (annual)13010070
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:55

Geo and Infrastructure Context

CityPoznan
Latitude52.4154
Longitude16.9472
Primary corridor length8.8 km
Stops/intersections affected18
Maintenance classPriority B
Program start year2018
Target completion year2022
Modal shift KPI10%
CO2 reduction KPI704 tons/year
Safety improvement KPI36%
Funding requested6,910,400 EUR
Funding secured5,676,400 EUR
Funding disbursed4,504,100 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 08:11:55

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 04:41:55

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-02 11:31:55

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Track renewal, platform reconfiguration, and rolling signal optimization for tram corridors. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.