Gdansk Smart Intersection Safety Program

City: Gdansk Impact: 77 Completion: 73% Budget: 4,690,000 EUR

Project Analytics

Beneficiaries (est.)

13,860

CO2 Reduction / year

528 t

On-time Confidence

76.4%

Readiness Index

75.6

Lifecycle Stage

Delivery

KPI Data Quality

100/100
Loading forecast panel...
Completion
73%
Impact Score
77
Budget Utilization (estimated)
67.16%
67.16%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
67
Incidents current (annual)
37

Baseline vs Current vs Target

Ridership (daily)449404952056100
Incidents (annual)1239363
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityGdansk
Latitude54.37
Longitude18.6686
Primary corridor length9.6 km
Stops/intersections affected18
Maintenance classPriority B
Program start year2017
Target completion year2021
Modal shift KPI24%
CO2 reduction KPI528 tons/year
Safety improvement KPI28%
Funding requested5,252,800 EUR
Funding secured4,314,800 EUR
Funding disbursed3,423,700 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 05:31:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-30 00:41:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-02 07:05:14

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Predictive signal logic, pedestrian priority cycles, and integrated incident response at key nodes. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.