Gdansk Tram Grid Modernization Package

City: Gdansk Impact: 71 Completion: 55% Budget: 4,320,000 EUR

Project Analytics

Beneficiaries (est.)

12,780

CO2 Reduction / year

484 t

On-time Confidence

62%

Readiness Index

65.4

Lifecycle Stage

Procurement

KPI Data Quality

100/100
Loading forecast panel...
Completion
55%
Impact Score
71
Budget Utilization (estimated)
50.6%
50.6%

Budget Allocation Graph

Circular utilization graph showing consumed versus remaining budget capacity.

Progress Trend (6 Checkpoints)

M1
M2
M3
M4
M5
M6

Safety Outcomes Graph

Incidents baseline (annual)
85
Incidents current (annual)
50

Baseline vs Current vs Target

Ridership (daily)436204796054300
Incidents (annual)1299969
KPI data sourceCity operations baseline audit and quarterly monitoring feed
Last KPI update2026-04-27 15:11:54

Geo and Infrastructure Context

CityGdansk
Latitude54.352
Longitude18.6466
Primary corridor length8.9 km
Stops/intersections affected14
Maintenance classPriority B
Program start year2022
Target completion year2026
Modal shift KPI22%
CO2 reduction KPI484 tons/year
Safety improvement KPI26%
Funding requested4,838,400 EUR
Funding secured3,974,400 EUR
Funding disbursed2,376,000 EUR

Delivery Timeline

  • Planning baseline approved and stakeholders aligned.
  • Procurement and partner mobilization completed.
  • Implementation phase in progress with weekly reporting.
  • Impact verification and community feedback checkpoint.

Citizen Sentiment

Support

0

Opposition

0

Total Responses

0

Operational Notes

City Operations Office - 2026-03-01 04:51:54

Monitoring checkpoint completed. KPI trajectory is on track with active risk mitigation for schedule pressure items.

Mobility Engineering Unit - 2025-08-29 23:41:54

Procurement and implementation package initiated. Utility coordination and temporary traffic management signed off.

Program PMO - 2025-03-02 05:58:34

Baseline corridor audit completed. Critical bottlenecks and quick-win segments approved by steering committee.

Track renewal, platform reconfiguration, and rolling signal optimization for tram corridors. Program spans baseline study, pilot deployment, staged construction, and benefits realization review.